Ernakulam: Due to line block to facilitate engineering works in Angamali – Ernakulam North section, train services will be rescheduled/regulated as mentioned below:
A. Rescheduling of train services
1. Train No 16128 Guruvayur – Chennai Egmore Express, scheduled to leave Guruvayur at 21.35 hrs., will be rescheduled to leave Guruvayur at 22.35 hrs (late by 1 hour) on 24th, 25th, 28th February and 01st & 02nd March, 2019.
2. On 27.02.2019, Train No 16128 Guruvayur – Chennai Egmore Express, scheduled to leave Guruvayur at 21.35 hrs., will be rescheduled to leave Guruvayur at 22.35 hrs (late by 1 hour). Further, the train will be regulated at Idappalli for 45 minutes.
B. Regulation of train services
1. Train No.16348 Mangalore – Thiruvananthapuram Central express will be regulated for 1 hour and 15 minutes at Kalamasseri on 24th, 25th, 28th February and 01st & 02nd March, 2019.
2. Train No.19260 Bhavnagar Terminus – Kochuveli express will be regulated for 2 hours at Idappalli on 25.02.2019.
3. On 27.02.2019, Train No.16348 Mangalore – Thiruvananthapuram Central express will be regulated for 2 hours and 05 minutes at Angamali.
4. On 27.02.2019, Train No.12432 Hazrat Nizamuddin – Thiruvananthapuram Central Rajdhani express will be regulated for 25 minutes at Alwaye.
5. Train No.16311 Shri Ganganagar – Kochuveli express will be regulated for 2 hours at Idappalli on 28.02.2019.
6. Train No.16360 Patna – Ernakulam Jn. express will be regulated for 2 hours at Kalamasseri on 28.02.2019.
7. Train No.16333 Veraval – Thiruvananthapuram Central express will be regulated for 2 hours at Idappalli on 01.03.2019.
8. Train No.16335 Gandhidham – Nagercoil express will be regulated for 2 hours at Idappalli on 02.03.2019.
9. Train No.16337 Okha – Ernakulam Jn. express will be regulated for 2 hours at Idappalli on 03.03.2019.
10. Train No.22634 Hazrat Nizamuddin – Thiruvananthapuram Central express will be regulated for 2 hours and 10 minutes at Kalamassery on 03.03.2019.
11. Train No.07115 Hyderabad – Kochuveli special train will be regulated for 2 hours at Kalamassery on 03.03.2019.
Wheather this line block to facilitate engineering works in Angamali – Ernakulam North section completed ?
Please publish in daily’s or website about the status